16-TON DOUBLE GIRDER OVERHEAD CRANE SYSTEM

  • Project name
    16-TON DOUBLE GIRDER OVERHEAD CRANE SYSTEM
  • Location
    Win Win Blvd, Bakheng Loeu Village, Sangkat Bakheng, Khan Chroy Changva, Phnom Penh Kingdom of Cambodia
  • Client
    Phnom Penh Water Supply Authority - EPC: Branch Of VINCI Construction Grands Projets S.A.S

The design, fabrication, and installation of this 16-ton Double Girder Overhead Crane system demonstrate the strategic synergy between FINE JSC’s specialized industrial fabrication—including piping systems (oil, water, air) and heavy steel structures—and the world-class lifting technology from the ABUS Group (Germany).

This project was successfully executed for the Bakheng Water Production Facilities Project (Stage 3) under the rigorous standards of Vinci Construction Grands Projets.

1. TECHNICAL SPECIFICATIONS & SCOPE

  • Equipment Type: Double Girder Overhead Crane.
  • Safe Working Load (SWL): 16 Tons.
  • Span: 14.55m (Customizable per project requirements).
  • Lifting Height: 15m.
  • Design Standards: FEM/DIN.

2. SUPPLY CAPABILITY & COMPONENT STRUCTURE

FINE JSC integrated high-performance ABUS (Germany) core systems:

  • Hoisting: Electric wire rope hoists with high durability and electronic overload protection.
  • Control: German-made panels, inverters, and festoon/busbar systems for absolute operational stability.

3. TURNKEY PROJECT MANAGEMENT

FINE JSC delivered a comprehensive "Turnkey" solution, ensuring accountability across the entire lifecycle:

Engineering & Structural Analysis

Advanced modeling for stress-strain, deflection, and Fatigue Analysis. This simulation optimizes the main girder's integrity, ensuring a long-term operational lifespan under real-world duty cycles.

Industrial Fabrication & Quality Control

  • Welding: Performed by DNV/AWS certified welders with 100% Non-Destructive Testing (NDT)—including Ultrasonic (UT) and Radiographic (RT)—on all critical joints.
  • Surface Protection: Abrasive blasting to Sa 2.5 followed by a high-performance 3-layer epoxy coating for maximum corrosion resistance.

Installation & Commissioning

Strategic logistics and precise onsite installation at the Bakheng site. Final commissioning was supervised by independent bodies.

4. PROJECT OUTCOMES

Completed on schedule for VINCI, the system delivers:

  • Reliability: Low-noise, stable operation via ABUS precision mechanisms.
  • Safety: Fully integrated sensors, anti-collision, and overload protection.
  • Support: Professional after-sales service and genuine German spare parts.

FINE JSC - Your Trusted Partner in Industrial Mechanical Fabrication, Lifting and Corrocoat's Anti-Corrossion Solutions.

  • Hotline: +84 (0)82 658 3979
  • Website: www.finejsc.com
  • Email: info@finejsc.com

 

20250912 083423

20250823 073657(1)

20251006 073537(1)

 

z7158382337858 88517644495ca7fbfe08bf816985e406

z7158344580462 0823a74ae264dd1123527d1d45d80b1d

z7158507561878 9d3c1596ec88496019eb29cfc3d93efa

 

  • ishare1
  • ishare2
  • ishare3

Contact us

We're here to help! Please fill out the form below, and our specialists will get in touch with you shortly to discuss your needs.